Development Project
Overview | Timeline | Plans | Funding | Suppliers | Voluntary Work | Opening | Photo Gallery | Virtual Tour | Thanks
Timeline - Milestones
| Year | Month | Phase | Module/Details | ||
| 2008 | Jun | Phase 4 | Garden | ||
| 22-Jun-08 | Volunteers install drainage and soak-away | ||||
| 21-Jun-08 | Volunteers improve guttering and prepare buttress foundations | ||||
| May | 31-May-08 | Volunteers prepare lawn | |||
| Phase 3 | Store Conversion | ||||
| 27-May-08 | Store Conversion completed | ||||
| Apr | 22-Apr-08 | AGM | |||
| Mar | |||||
| Feb | |||||
| Jan | |||||
| 2007 | Nov | ||||
| Oct | 17-Oct-07 | Store Conversion started | |||
| 10-Oct-07 | Golden Seal appointed to undertake Store Conversion | ||||
| Sep | 07-Sep-07 | Invitations to tender issued for Store Conversion | |||
| Aug | 05-Aug-07 | Plans of existing and proposed Store drawn up | |||
| Jul | 29-Jul-07 | Store surveyed | |||
| Jun | |||||
| May | 08-May-07 | AGM - Presentation describing progress | |||
| 05-May-07 | First bunkhouse guests! 18 Kite Surfers from Southampton University | ||||
| Apr | Phase 2 | Kitchen, Bunkhouse, Meeting Room Fitting Out | |||
| 16-Apr-07 | Final Certificate issued for Bunkhouse | ||||
| Mar | 31-Mar-07 | Official Opening by the First Minister, the Rt Hon Rhodri Morgan AM | |||
| Mar-07 | Bunkhouse equipped & decorated by community volunteers | ||||
| 01-Mar-07 | Completion Certificate issued for Building | ||||
| Feb | |||||
| Jan | 11-Jan-07 | Kitchen fitting completed | |||
| 2006 | Dec | ||||
| Nov | 27-Nov-06 | Bunkhouse Plans drawn up | |||
| Oct | 21-Oct-06 | Golden Seal appointed to partition and fit out Bunkhouse | |||
| Gower Coast appointed to fit out Meeting room and undertake External Works | |||||
| 14-Oct-06 | RACS appointed to fit Kitchen | ||||
| Sep | 24-Sep-06 | Invitations to tender issued for Kitchen, Bunkhouse & Meeting Room | |||
| 11-Sep-06 | WAG CFAP Funding for Phase 2 £75,890 Granted | ||||
| Aug | 09-Aug-06 | Committee visits Allison Tyrrell at Hardingsdown Bunkhouse | |||
| Jul | 26-Jul-06 | WAG CFAP Funding for Phase 2 approved in principle | |||
| Phase 1 | Building Design & Construction | ||||
| 04-Jul-06 | Visit by Their Royal Highnesses The Prince of Wales & Duchess of Cornwall | ||||
| - Gathering to Celebrate 50th Anniversary of the UK's First AONB | |||||
| Jun | Jun-06 | Hall redecorated by community volunteers | |||
| May | |||||
| Apr | 27-Apr-06 | AGM - Presentation describing next steps | |||
| 17-Apr-06 | Re-Applied for WAG CFAP Funding for Phase 2 | ||||
| - Provided 26 letters of support from local businesses, groups and individuals | |||||
| Mar | 24-Mar-06 | Application for WAG CFAP Funding for Phase 2 Rejected | |||
| Awards for All Wales Grant of £5,000 awarded for furniture and equipment | |||||
| Feb | 02-Feb-06 | WEFO Article 4 Audit of expenditure | |||
| Jan | |||||
| 2005 | Dec | ||||
| Nov | 14-Nov-05 | Application for WAG CFAP Funding for Phase 2 submitted | |||
| Oct | 12-Oct-05 | Construction of new building started | |||
| Sep | 22-Sep-05 | Asbestos Inspection by Anchem Laboratories | |||
| Aug | |||||
| Jul | 29-Jul-05 | Tenders received and Cambrian Construction selected | |||
| Jun | 27-Jun-05 | Invitations to tender issued for building construction | |||
| 24-Jun-05 | Objective 1 Funding Granted | ||||
| May | |||||
| Apr | 21-Apr-05 | AGM - Presentation describing project | |||
| Mar | 10-Mar-05 | Objective 1 Funding Approved subject to acceptance of offer | |||
| 07-Mar-05 | Additional information provided to WEFO | ||||
| Feb | 11-Feb-05 | Additional information provided to WEFO | |||
| 11-Feb-05 | Bank confirms offer of loan to meet funding shortfall | ||||
| Jan | 21-Jan-05 | Meeting with WEFO and SCC | |||
| 04-Jan-05 | Site Investigation by Dean & Thomas | ||||
| 2004 | Dec | ||||
| Nov | 05-Nov-04 | Application to WEFO for EU Objective 1 Funding | |||
| Oct | |||||
| Sep | |||||
| Aug | |||||
| Jul | 20-Jul-04 | Fitting out of Kitchen etc removed from Phase 1 to keep project affordable | |||
| Jun | |||||
| May | |||||
| Apr | AGM - Presentation given to Swansea Local Partnership in May-03 | ||||
| Mar | 30-Mar-04 | WDA Funding £40,000 received for Hall Refurbishment | |||
| - New central heating; curtains & blinds; chairs & tables; screen etc | |||||
| Feb | |||||
| Jan | 14-Jan-04 | Planning permission granted by the City & County of Swansea | |||
| 05-Jan-04 | Full Planning application for permission to carry out the development | ||||
| 2003 | Dec | Dec-04 | Plans amended and finalised | ||
| Nov | 12-Nov-03 | WEFO approval given to apply for Objective 1 funding | |||
| Oct | |||||
| Sep | |||||
| Aug | |||||
| Jul | |||||
| Jun | |||||
| May | 16-May-03 | Presentation to Swansea Local Partnership (EU) Rural Assets Sub-Group | |||
| - Asked for 50% EU Objective 1 funding towards project costs | |||||
| Apr | 26-Apr-03 | Total Project costs estimated at £313,333 | |||
| Mar | |||||
| Feb | |||||
| Jan | |||||